Operational program: Competitiveness and cohesion 2014-2020

Project name: Installation of the solar panel system for production purposes in Omco Croatia

On November 23rd 2017 Omco Croatia d.o.o. started with installation of the solar panel system for own purposes. It is planned and had been installed a solar panel system with 1000kW of installed power on the AC side.

Solar panel system contains 4530 photovoltaic panels with nominal power of 270W. With project implementation there will be a reduction of the grid consumption and usage of the energy from the conventional power plants as part of energy balance will be covered by renewable sources.

Goals and expected results of the project: Energy consumption for the observed business unit which is part of the project is 3.872.015 kWh covered by grid supply. By the project, annual energy production of the solar panel system is 1.247.965 kWh. With projected energy production the system will reduce energy consumption from the grid by 32,23% of the business unit. This will also have an impact on the reduction of CO2 emission in amount of 293,03 ton.

Total estimated project value is 9.431.275,00 HRK.
Total estimated subsidy amount from EU is 5.552.615,00 HRK.
Project implementation period: 23.11.2017. - 31.12.2020.

Contact person for more information:
Domagoj Dosen, domagoj.dosen@omcomould.com , +38549327405
http://www.strukturnifondovi.hr
https://strukturnifondovi.hr/eu-fondovi/esi-fondovi-2014-2020/op-konkurentnost-i-kohezija/

This project is co-financed by the European Union from the European Regional Development Fund